Mathematics · Project Management and PERT Analysis
एक गतिविधि के लिए: आशावादी समय (Optimistic time) = 3 दिन सर्वाधिक संभावित समय (Most likely time) = 9 दिन निराशावादी समय (Pessimistic time) = 15 दिन गतिविधि का प्रसरण (Variance) है:
- 16
- 24✓
- 32
- 41
सही उत्तर देखें