Computer Science · Software Project Management
You are leading a new IT project with a very tight deadline. The client insists on implementing 10 features in 6 weeks. Your team estimates that only 7 features can be completed in this timeframe. The client refuses to reduce the scope, and your developers are worried about burnout. What should you do first as a project manager?
- 1Remove the less experienced members of the team to increase speed.
- 2Start working on all 10 features simultaneously with full effort.
- 3Use a prioritization methodology to negotiate the critical features for delivery after discussing with the client.✓
- 4Accept the client's demand and ask the team to work overtime.
Correct answer
Use a prioritization methodology to negotiate the critical features for delivery after discussing with the client.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer Science?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Software Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer Science · Software Project Management