X can finish a work in 153 days, Y can finish the same work in 255 days, and Z can finish it in 340 days. How many days will they require to complete the work if X, Y, and Z work together?
- 12896 41 days
- 22978 41 days
- 33142 41 days
- 43060 41 days✓
Correct answer
3060 41 days