Mathematics · Time and Work
X can finish a work in 153 days, Y can finish the same work in 255 days, and Z can finish it in 340 days. How many days will they require to complete the work if X, Y, and Z work together?
- 1722641
- 2762641
- 3742641✓
- 47041
Correct answer
742641
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Time and Work?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Time and Work