Mathematics · Time and Work
'X' can complete a work order in 15 days and 'Y' can complete the same work order in 12 days. With the help of 'F', the three of them finished the work in 5 days. How many days would 'F' take to complete the work alone?
- 15 days
- 210 days
- 320 days✓
- 415 days
Correct answer
20 days