X can complete 40% of a work in 12 days, whereas Y can do 60% of the same work in 15 days. Both work together for 10 days. Z completes the remaining portion of the work alone in 4 days. In how many days will X, Y, and Z together complete 28% of the same work?
- 13 days
- 2212 days
- 32 days✓
- 4112 days
Correct answer
2 days