X and Y can complete a work in 12 days and 18 days respectively. They started working together, but after 4 days Y had to leave and X alone completed the remaining work. In how many days was the entire work completed?
- 118 days
- 210 days
- 315 3 days
- 428 3 days✓
Correct answer
28 3 days