Mathematics · Time and Work
Working alone, A can complete a task in 30 days. After working for 10 days, A left the task, and B alone completed the remaining work in 32 days. In how many days can A and B complete the task working together?
- 120613
- 215613
- 318613✓
- 413613
Correct answer
18613