Worker A requires 16 days to prepare a playground, while worker B can complete the same task in 12 days. When A, B, and a third worker C collaborate, they finish the entire job in 4 days. How long will it take worker C to complete the work alone?
- 110 days
- 28 days
- 39.6 days✓
- 49.6 days
Correct answer
9.6 days