Which statement about Materials Requirement Planning (MRP) is incorrect?
- 1MRP relies solely on historical sales data and trend extrapolation for its material requirement calculations.✓
- 2MRP systems require accurate lead time information for effective component planning.
- 3MRP systems help manage inventory levels of dependent demand items and production schedules.
- 4MRP can improve customer service by ensuring finished product availability.
Correct answer
MRP relies solely on historical sales data and trend extrapolation for its material requirement calculations.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Industrial Engineering and Operations Research?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Industrial Engineering and Operations Research