Computer · Construction Management
Which process involves the intelligent utilization of floats to smooth out the demand for resources without extending the total project duration?
- 1Resource aggregation
- 2Resource levelling
- 3Resource smoothing✓
- 4Resource allocation
Correct answer
Resource smoothing