Computer · Construction Management
Which phase of a construction project project-lifecycle primarily involves forming and organizing the core project team, defining tasks, and establishing work breakdown structures?
- 1Construction controlling
- 2Construction planning✓
- 3Construction monitoring
- 4Construction scheduling
Correct answer
Construction planning