Which one of the following statements is NOT correct regarding total float in network analysis?
- 1Total float of an activity is obtained by subtracting its early start time from its late start time.
- 2Subtracting the early finish time from the late finish time provides the total float.
- 3Activities with zero total float are called critical activities.
- 4Total float can be calculated by subtracting its early finish time from the earliest of the early start times of the activities directly following it.✓
Correct answer
Total float can be calculated by subtracting its early finish time from the earliest of the early start times of the activities directly following it.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Project Management