Which one of the following statements is NOT correct regarding a traditional Gantt chart?
- 1Illustrations indicate how activities are distributed over the project timeline.
- 2The chart explicitly demonstrates the complex interdependencies and operational concurrency of a large project.✓
- 3The beginning and end of a bar coincide with the activity's starting and ending dates.
- 4Activities are illustrated as bars on a horizontal timeline.
Correct answer
The chart explicitly demonstrates the complex interdependencies and operational concurrency of a large project.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Project Management