Which one of the following statements is NOT correct regarding a line-of-balance schedule?
- 1Using a combination of sloping lines, bars, and blocks, operations can be sequenced so that space and resource conflicts are identified.
- 2It is primarily suited for non-repetitive, unique infrastructure projects where operations cannot be sequenced.✓
- 3It is a highly visual method of representing repetitive types of projects.
- 4It represents both a presentation format and a scheduling technique.
Correct answer
It is primarily suited for non-repetitive, unique infrastructure projects where operations cannot be sequenced.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Project Management