Physics · Construction Management
Which one of the following statements is NOT a true necessity or characteristic of construction specifications?
- 1Specification has no impact on changes of cost of materials and tools, i.e., the tender rate✓
- 2Specification is an essential contract document and is required for arbitration purposes
- 3Specification is necessary to specify the equipment, tools and plants to be engaged for a work and enables procuring them beforehand
- 4Specification of a work is required to specify the quality and quantity of different materials required and is an essential contract document
Correct answer
Specification has no impact on changes of cost of materials and tools, i.e., the tender rate
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Physics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Physics · Construction Management