Which one of the following statements is correct regarding the Program Evaluation and Review Technique (PERT)?
- 1PERT is a purely deterministic approach for estimating the time duration of an activity.
- 2PERT does not provide probabilistic time durations.
- 3PERT is suitable for the estimation of activity duration where high levels of uncertainty exist.✓
- 4PERT is commonly used for routine construction work.
Correct answer
PERT is suitable for the estimation of activity duration where high levels of uncertainty exist.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Project Management