Which one of the following statements is correct regarding project management techniques?
- 1A project schedule is a rough timetable of construction operations.
- 2PERT is a method of statistically evaluating project duration over a time-sensitive domain.✓
- 3PERT is developed for the quality control laboratory work at construction sites.
- 4CPM is developed especially for scheduling of research and development work.
Correct answer
PERT is a method of statistically evaluating project duration over a time-sensitive domain.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Project Management