Which one of the following is NOT considered standard practice for the estimation of activity duration in project planning?
- 1Normal weather conditio ns are considered for the estimation of duration of each activity.
- 2If time units of working days are being used, assume an exceptional day with maximum working hours.✓
- 3For each activity, assume a normal level of manpower and/or equipment.
- 4Evaluate activities one at a time, independently of all others.
Correct answer
If time units of working days are being used, assume an exceptional day with maximum working hours.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Project Management