Economics · Project Management
Which one is the correct chronological sequence of procedures to be adopted to purchase the material desired for the completion of a project once the quotations are called for?
- 1Purchase order, Comparative statements, Inspection of material, Release of payment
- 2Comparative statements, Inspection of material, Purchase order, Release of payment
- 3Comparative statements, Purchase order, Inspection of material, Release of payment✓
- 4Inspection of material, Comparative statements, Purchase order, Release of payment
Correct answer
Comparative statements, Purchase order, Inspection of material, Release of payment
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Economics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Economics · Project Management