Computer · PERT and CPM
Which of the following time estimates in project management does NOT include any provision for delays and setbacks?
- 1Pessimistic time estimate
- 2Expected time estimate
- 3Optimistic time estimate✓
- 4Most likely time estimate
Correct answer
Optimistic time estimate