Which of the following statements regarding PERT and CPM is INCORRECT?
- 1For projects with predictable activities, CPM is a good fit.
- 2PERT focuses on events, whereas CPM focuses on activities.
- 3PERT and CPM are both event-oriented methodologies.✓
- 4PERT is appropriate for projects with uncertain time predictions.
Correct answer
PERT and CPM are both event-oriented methodologies.