Which of the following statements regarding network planning techniques is incorrect?
- 1None of these✓
- 2An event is an instantaneous point in time at which an activity begins or ends.
- 3The performance of a specific task is called an activity.
- 4An activity consumes time and resources, whereas an event does not consume time or resources.
Correct answer
None of these