Which of the following statements is true for CPM when compared to PERT?
- 1It is used for non-repetitive jobs.
- 2It indirectly introduces the concept of cost into the analysis.
- 3It does not incorporate statistical analysis in determining time estimates.✓
- 4Under CPM convention, each event is represented by a circle and arrows are used to indicate activities.
Correct answer
It does not incorporate statistical analysis in determining time estimates.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Management