Which of the following statements is NOT true regarding the Program Evaluation and Review Technique (PERT)?
- 1It is an activity-oriented or process-oriented technique.✓
- 2It is a statistical tool that handles uncertainty in activity duration.
- 3It is a project management tool.
- 4It is a network-based model.
Correct answer
It is an activity-oriented or process-oriented technique.