Which of the following statements is NOT correct about the Program Evaluation and Review Technique (PERT)?
- 1PERT was developed during the late 1950s.
- 2PERT utilizes three time estimates: optimistic, most likely, and pessimistic.
- 3In a PERT chart, 'Nodes' represent the activities or tasks, while 'Arrows' represent events or milestones.✓
- 4PERT was developed primarily to simplify the planning and scheduling of large, complex, and uncertain projects.
Correct answer
In a PERT chart, 'Nodes' represent the activities or tasks, while 'Arrows' represent events or milestones.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Project Management