Which of the following statements is INCORRECT regarding the Critical Path Method (CPM)?
- 1It is ideally used for repetitive types of projects.
- 2Only a single-time estimate is made for each activity.
- 3It is deterministic in nature.
- 4It is an event-oriented approach.✓
Correct answer
It is an event-oriented approach.