Which of the following statements is FALSE regarding the Critical Path Method (CPM)?
- 1It is an event-oriented technique.✓
- 2It is deterministic in nature and ignores chance elements.
- 3It is predominantly used for construction projects.
- 4It is an activity-oriented technique.
Correct answer
It is an event-oriented technique.