Electrical Engineering · Transformers
Which of the following statements is correct regarding the open-circuit and short-circuit tests performed on a single-phase transformer?
- 1The open-circuit test is primarily used to determine iron losses.✓
- 2The short-circuit test is primarily used to determine core losses.
- 3For the open-circuit test, the low-voltage side is kept open.
- 4For the short-circuit test, the measuring instruments should ideally be connected on the low-voltage side.
Correct answer
The open-circuit test is primarily used to determine iron losses.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Electrical Engineering?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Transformers?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Electrical Engineering · Transformers