Which of the following statements is correct regarding project management techniques?
- 1All of the given options✓
- 2The critical path of a network represents the minimum time required for the completion of the project.
- 3The CPM technique is useful to minimize direct and indirect expenses.
- 4When the float of an activity is zero, it falls only on the critical path.
Correct answer
All of the given options