Computer · PERT and CPM
Which of the following statements is correct regarding network analysis in project management?
- 1A dummy is a type of operation which neither requires time nor any resource.✓
- 2The activities which can be started one after another are known as parallel activities.
- 3A tail event or a start event of a project has only incoming arrows.
- 4Serial activities can exist simultaneously or concurrently.
Correct answer
A dummy is a type of operation which neither requires time nor any resource.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on PERT and CPM?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · PERT and CPM