Which of the following statements is correct regarding errors in chain surveying?
- 1When the pull applied while measuring with a tape is more than the standard pull, the error in the measured length is a positive error.
- 2The error in measured length due to careless holding of the chain is a cumulative error.
- 3If the chain used in measuring a distance is too short, the error in the recorded measurement is a positive error.✓
- 4The error in measured length due to bad ranging is a compensating error.
Correct answer
If the chain used in measuring a distance is too short, the error in the recorded measurement is a positive error.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Surveying?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Surveying