Which of the following statements are correct regarding the PERT and CPM techniques? A. Both techniques use a similar network structure but serve different project types. B. Both techniques were developed independently of each other during the late 1950s. C. PERT was developed and used in conjunction with the planning and designing of the Polaris submarine system. D. CPM was developed by the Du Pont Company. E. Both PERT and CPM techniques are utilized in both the planning and controlling stages of a project. Choose the correct answer from the options given below:
- 1A, B, C, D, and E✓
- 2A, C, and E only
- 3B, D, and E only
- 4A, B, and C only
Correct answer
A, B, C, D, and E
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Project Management