Which of the following statements accurately distinguishes CPM (Critical Path Method) from PERT (Programme Evaluation and Review Technique)?
- 1PERT is used only for small residential construction, while CPM is used for space exploration.
- 2CPM employs a probabilistic approach, whereas PERT uses a deterministic approach.
- 3PERT focuses solely on activity cost optimization, whereas CPM focuses on safety parameters.
- 4CPM is deterministic and used for projects with well-defined activities, while PERT is probabilistic and used for projects with uncertain activity durations.✓
Correct answer
CPM is deterministic and used for projects with well-defined activities, while PERT is probabilistic and used for projects with uncertain activity durations.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Management