Computer · Construction Management
Which of the following statements accurately distinguishes between CPM (Critical Path Method) and PERT (Programme Evaluation and Review Technique)?
- 1PERT is generally used for construction projects, while CPM is used for software development projects.
- 2CPM employs a probabilistic approach to time estimation, whereas PERT uses a deterministic approach with fixed activity durations.
- 3PERT focuses on the optimization of the cost of activities, whereas CPM focuses on optimizing the project schedule.
- 4CPM is primarily used for projects with well-defined activities and deterministic time estimates, while PERT is used for projects with uncertain activities and probabilistic time estimates.✓
Correct answer
CPM is primarily used for projects with well-defined activities and deterministic time estimates, while PERT is used for projects with uncertain activities and probabilistic time estimates.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Management