Computer · Construction Management
Which of the following statements accurately distinguishes between CPM (Critical Path Method) and PERT (Program Evaluation and Review Technique)?
- 1CPM is used for deterministic projects with well-defined activity durations, whereas PERT is used for probabilistic projects with uncertain activity durations.✓
- 2PERT focuses primarily on activity cost optimization, whereas CPM focuses solely on schedule optimization.
- 3CPM employs a probabilistic approach, whereas PERT uses a deterministic approach.
- 4PERT is restricted to civil construction, whereas CPM is used for software development.
Correct answer
CPM is used for deterministic projects with well-defined activity durations, whereas PERT is used for probabilistic projects with uncertain activity durations.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Management