Computer · Estimation and Costing
Which of the following methods is NOT used for calculating the quantities of materials in building estimation?
- 1Centre line method
- 2Long and short wall method
- 3Straight line method✓
- 4Crossing method
Correct answer
Straight line method
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Estimation and Costing?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Estimation and Costing