Which of the following is used to determine the Cost Performance Index (CPI) in project management?
- 1Budgeted cost of work performed - Actual cost of work performed
- 2Budgeted cost of work performed ÷ Actual cost of work performed✓
- 3Budgeted cost of work performed ÷ budget at completion
- 4Budgeted cost of work performed - budget at completion
Correct answer
Budgeted cost of work performed ÷ Actual cost of work performed
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer Science?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Software Engineering?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer Science · Software Engineering