Which of the following is true regarding PERT and CPM network techniques?
- 1CPM employs two cost estimates and no time estimate.
- 2PERT employs three time estimates and no cost estimate.✓
- 3CPM employs one cost and two time estimates.
- 4PERT employs one time and one cost estimate.
Correct answer
PERT employs three time estimates and no cost estimate.