General Studies · Project Management
Which of the following is true about the Critical Path Method (CPM) in project management?
- 1It is a probabilistic method.
- 2It focuses on minimizing resource usage.
- 3Activities on the critical path have zero slack time.✓
- 4The critical path is the shortest path in the network.
Correct answer
Activities on the critical path have zero slack time.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Project Management