Computer Science · Software Engineering
Which of the following is the correct software cost/effort estimation model based on the software equation (put forward by Putnam)?
- 1E = [LOC × B0.222 / P]2 × (1 / t4)
- 2E = [LOC × B0.333 / P]3 × (1 / t4)✓
- 3E = [LOC × B0.444 / P]4 × (1 / t3)
- 4E = [LOC × B0.111 / P]6 × (1 / t3)
Correct answer
E = [LOC × B0.333 / P]3 × (1 / t4)