Which of the following is NOT a typical phase of project planning in construction management?
- 1Detailed project planning and scheduling
- 2Procurement and material supply chain auditing✓
- 3Project identification and feasibility study
- 4Execution planning and resource allocation
Correct answer
Procurement and material supply chain auditing