Which of the following is NOT a recognized classification or standard term for inter-activity relationship in PERT or CPM network analysis?
- 1Intermediate predecessor activity
- 2Processing activity✓
- 3Preceding activity
- 4Predecessor activity
Correct answer
Processing activity