Which of the following is NOT a primary reason or requirement for running transformers in parallel operation?
- 1To ensure continuous power supply during maintenance
- 2It is more economical to manufacture a single very high-rating transformer than multiple smaller ones✓
- 3To meet the increased load demand that exceeds the capacity of an existing transformer
- 4To improve the overall efficiency of the power system under varying load conditions
Correct answer
It is more economical to manufacture a single very high-rating transformer than multiple smaller ones
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Electrical Engineering?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Parallel Operation of Transformers?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Electrical Engineering · Parallel Operation of Transformers