Which of the following is NOT a characteristic of the Program Evaluation and Review Technique (PERT)?
- 1It utilizes three time estimates to manage uncertainty in task durations.
- 2It is a deterministic approach that assumes fixed activity durations for cost optimization.✓
- 3PERT assists in various stages of non-repetitive project management.
- 4PERT provides the critical path and slack time for project activities.
Correct answer
It is a deterministic approach that assumes fixed activity durations for cost optimization.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Project Management