Which of the following is considered a limitation or weakness of a traditional bar chart (Gantt chart)?
- 1All of the above✓
- 2Does not incorporate uncertainties and probabilities explicitly
- 3Does not easily show detailed project progress for complex projects
- 4Does not clearly show the interdependence of activities
Correct answer
All of the above