General Studies · Project Management
Which of the following is an incorrect statement regarding PERT and CPM?
- 1PERT is event-oriented, while CPM is activity-oriented.
- 2Both PERT and CPM are event-oriented.✓
- 3CPM is suitable for projects having deterministic activities.
- 4PERT is suitable for projects having probabilistic time estimates.
Correct answer
Both PERT and CPM are event-oriented.