Physics · Industrial Engineering
Which of the following is a primary benefit of using Program Evaluation and Review Technique (PERT) in project management?
- 1Offers a structured method for keeping project planning current
- 2Provides a tool to ensure planning is done consistently and logically
- 3All of the options (predicting changes, logical planning, and keeping plans current)✓
- 4Enables management to predict the effects of changes to the plan promptly
Correct answer
All of the options (predicting changes, logical planning, and keeping plans current)
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Physics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Industrial Engineering?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Physics · Industrial Engineering