Which of the following is a major limitation of using a bar chart (Gantt chart) in construction scheduling?
- 1It is highly complex and time-consuming to prepare.
- 2It cannot represent the progress of work over time.
- 3It cannot clearly show the interdependence of activities.✓
- 4It is difficult to understand by field personnel.
Correct answer
It cannot clearly show the interdependence of activities.