Computer · Project Management - PERT/CPM
Which of the following is a key functional advantage of using network techniques like PERT/CPM in project management?
- 1It guarantees project completion exactly on time and within the estimated budget
- 2It helps to identify critical activities that need close monitoring to prevent delays✓
- 3It automatically shortens the duration of non-critical activities
- 4It entirely eliminates all financial and operational risks of a project
Correct answer
It helps to identify critical activities that need close monitoring to prevent delays
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management - PERT/CPM?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Project Management - PERT/CPM